Overbilling and underbilling explained
Every open job on a WIP schedule is either billed ahead of the work, behind it, or right on it. The difference is called an overbilling or an underbilling, and it is one of the first numbers a surety or banker looks at when they open your financials.
Blake Richardson, Founder, KBRC · Updated
The calculation
Start with earned revenue, which is the contract amount times percent complete. Compare it to what you have billed to date on the same job.
- Billed more than earned: the job is overbilled. The difference is billings in excess of costs and estimated earnings.
- Earned more than billed: the job is underbilled. The difference is costs and estimated earnings in excess of billings.
A quick example. A $1,000,000 contract is 40% complete, so earned revenue is $400,000. If you have billed $450,000, the job is overbilled by $50,000. If you have billed $350,000, it is underbilled by $50,000.
Where they land on the balance sheet
Overbillings are a liability. You have been paid, or can bill, for work you have not yet done, and you owe that work to the customer. Underbillings are an asset. You have done work you have not yet billed for.
Those two balance sheet lines should equal the totals on your WIP schedule. When they do not, either the WIP or the books are wrong, and that mismatch is one of the most common problems found when a contractor's financials are reviewed. The monthly entry that keeps them in sync is covered in the percent complete adjustment.
Why overbilling is usually normal
Contractors who bill on a schedule of values with front-loaded line items, mobilization, or stored materials will run modestly overbilled on most jobs. That is the operating norm, and it helps cash flow.
The risk is treating overbilling cash as profit. That money is already committed to finishing the work. A company that spends its overbillings to cover overhead or other jobs can look healthy right up until the back half of its projects need funding.
Why underbilling is a warning sign
Underbilling can be innocent. A change order is approved but not yet billed, or the billing cycle simply falls before month end. But a job that stays underbilled, or grows more underbilled month after month, usually points to something else:
- Costs are running over the estimate, so the cost-to-cost percent complete races ahead of what the work actually supports.
- Unapproved change order work is being done and carried as if it will be paid.
- Billing is lagging because nobody owns it.
Sureties and lenders read persistent underbilling as possible unrecognized losses. It is the line they ask about first.
What to do with the numbers
Look at overbilling and underbilling by job, not just in total. A small net figure can hide one badly underbilled job offset by several overbilled ones. Review the trend each month alongside estimated gross profit, and ask the project manager about any job whose underbilling grew.
That review only works if the WIP is updated every month. See the monthly close checklist for where it fits.
Common questions
- Is overbilling illegal or unethical?
- No. In this context overbilling is an accounting term for billing ahead of earned revenue under your contract terms, which is common and expected. It does not mean charging a customer more than the contract allows.
- Is underbilling an asset or a liability?
- An asset. It represents work performed that you have earned but not yet billed. It is usually shown as costs and estimated earnings in excess of billings.
- Should overbillings and underbillings be netted?
- On the WIP schedule they are calculated per job. On the balance sheet the total overbillings and total underbillings are typically shown separately rather than netted, so the size of each is visible. Your CPA decides the final presentation.